If Rs. 44000 was invested in scheme C at the rate of (R+2)% per annum on simple interest then an amount Rs. 39600 will be obtained as an interest after 6 years. 44000x(R+2)%x6 = 39600 [44000x(R+2)x6]/100 = 39600 [440x(R+2)x6] = 39600 2640x(R+2) = 39600 (R+2) = 15 R = 15-2 R = 13 John invested Rs. (P-4000) and Rs. (P+5000) in scheme A and scheme B respectively. The rate of interest in scheme A and B is (R+1)% and (R-1)% respectively and each of the schemes is on simple interest. After eight years, the interest obtained from scheme B is Rs. 2880 more than that of scheme A. (P-4000)x(R+1)%x8 + 2880 = (P+5000)x(R-1)%x8 Put the value of ‘R’ in the above given equation. (P-4000)x(13+1)%x8 + 2880 = (P+5000)x(13-1)%x8 (P-4000)x14%x8 + 2880 = (P+5000)x12%x8 [(P-4000)x14x8]/100 + 2880 = [(P+5000)x12x8]/100 [(P-4000)x112]/100 + 2880 = [(P+5000)x96]/100 [(P-4000)x112] + 288000 = [(P+5000)x96] 112P-448000+288000 = 96P+480000 112P-96P-160000 = 480000 16P = 480000+160000 16P = 640000 Value of ‘P’ = 40000
‘D’ and ‘E’ can complete a project in 40 days, while ‘E’ and ‘F’ can complete it in 60 days. ‘D’ and ‘E’ worked together on it f...
A can complete a job in 20 hours. B alone can complete the same job in 15 hrs. A work for 9 hrs and then the remaining job is completed by B. How many h...
The ratio of time taken by P, Q and R to complete work alone is 6:8:3 respectively. If all three together complete the work in 5 days, then find in how ...
Amisha is 50% more efficient than Khushi. Amisha started a work, worked for 'w' days and then Khushi replaced Amisha. khushi completed the remaining wor...
Suraj is one third as good as workman as Pankaj and together they finish a piece of work in 36 days. The number of days taken by Suraj alone to finish t...
'A' takes 7 times as much time as 'B' takes or 3 times as much time as 'C' takes to finish a piece of work. Working together, they can finish the work ...
'Preeti' can complete a piece of work in 70 days, while 'Bhanumati' can complete it in 90 days. They both started the work together, but 'Preeti' left a...
P can do a piece of work in 25 days, Q can complete double the work in 40 days and R can do the work in 30 days. If all of them together earn Rs. 7400, ...
Efficiency of A is 25% more than B and B takes 30 days to complete a piece of work. A started the work alone and then B joined him 4 days before actual ...
A can do a work in 45 days and the same the work is done in 15 days by A and B together, then in how many days B can complete the 20% of work?