ЁЯУв Too many exams? DonтАЩt know which one suits you best? Book Your Free Expert ЁЯСЙ call Now!


    Question

    'A' can do some work alone in 16 days. 'A'and 'B' work

    together for 8 days after which'A' leaves and 'B' finishes the remaining work alone in 12 days. How much time does 'B' need to finish the work alone?
    A 40 days Correct Answer Incorrect Answer
    B 30 days Correct Answer Incorrect Answer
    C 45 days Correct Answer Incorrect Answer
    D 25 days Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    ATQ, Let the efficiency of 'A' be 'a' units/day. So, total work = 16 ├Ч a = '16a' units So, work done by 'A' in 8 days = a ├Ч 8 = '8a'units So, work done by 'B' = 16a - 8a = '8a' units So, efficiency of 'B' = 8a ├╖ (12 + 8) = '0.4a'units/day So, required time = 16a ├╖ 0.4a = 40 days

    Practice Next
    More Time and distance Questions
    ask-question