Question
Arijit, Benny, and Chetna together can complete a work in 12 days. If the ratio of the efficiency of Arijit, Benny, and Chetna is 8:5:6, respectively, then find the time taken by Arijit alone to complete the whole work.
More Time and distance Questions
- A diesel truck travelled for 10 hours with a speed of 35 km/h. If the truck travels for 5 km per 1 litre of diesel, then find the quantity of diesel used b...
- A person crosses a 2400 m long street in 12 min. What is his speed (in km/h)?
- A train is travelling at the rate of 90 km/hr. How many seconds it will take to cover a distance of 5/8 km?
- A was travelling from point X to point Y. He increased his speed by 12 km/h after every hour. He reached his destination in 16 hours. If his initial speed ...
- 'A' can do some work alone in 16 days. 'A'and 'B' work together for 8 days after which'A' leaves and 'B' finishes the remaining work alone in 12 days. How ...
- A boy goes to school with a speed of 85 km/h and comes back with a speed of 40 km/h. find his average speed?
- Two trains starts at the same time from Spain and France towards each other with a speed of 160km/hr and 190 km/hr. When they meet, the faster train covers...
- How many km per hour does a man walk who passes through a street 1400 m long in 12 minutes?
- A car travels 225 km in 5 hours at its normal speed. If it covers 90 km at this regular speed and then travels another 135 km at a speed that is 20% faster...
- Rita walks from her home to office. If she walks at 8 km/h, she arrives 20 minutes late. But if she walks at a speed of (5/2) m/s, she gets there just 5 mi...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt