Question
A, B, and C together can complete a task in 24 days. A
and B together can complete it in 36 days, and B and C together can complete it in 48 days. How many days will it take for A alone to complete the task?Solution
Let the rates of A, B, and C be A, B, and C respectively. A + B + C = 1/24 A + B = 1/36 B + C = 1/48 Subtract (B + C) from (A + B + C): A = (1/24 - 1/48) = 1/48. A = 1/48. So, A alone will take 48 days to complete the task. Correct Option: d
Which river is the longest in Asia?
Where did the 1st All India Annual States' Ministers Conference on "Water Vision@2047 held on 5 - 6 Jan, 2023?
Virzu Studios in cooperation with MIDAS Deals Pvt Ltd has released the motion poster of its upcoming graphic novel, Atharva – The Origin, who is t...
‘World Chess Day’ is observed annually on which day of July month?
Who has clinched the WTA Chennai Open title 2022 ?
A Great Knot, a migratory bird has flown over 9, 000 km from Russia to which of the Indian state recently?
What was India's external debt at end March 2024?
Which of the following districts of Uttar Pradesh is famous for chikankari work and zari work?
Mount St. Helens, an active stratovolcano, is located in which country?
Who is the recipient of UNESCO Peace Award?