Question
A can do a piece of work in 28 days, while B can do the same piece of work in 42 days. They begin working together and 6 days before completion of work, A leaves. Find the total number of days taken to complete the work.
More Time and work Questions
- 'Preeti' can complete a piece of work in 70 days, while 'Bhanumati' can complete it in 90 days. They both started the work together, but 'Preeti' left afte...
- Priya alone can paint a wall in 30 days. Priya and Neha together can do it in 18 days. How many days would Neha take to paint the wall by herself?
- Pawan and Qureshi can individually complete a certain task in 5 hours and 15 hours, respectively. Pawan begins the task at 9:00 a.m., and they work alterna...
- Anmol can do a piece of work in 30 days, Bineet can complete double the work in 90 days and Chintu can do the work in 60 days. If all of them jointly gets ...
- A man, a woman and a boy can do a work in 3, 2, 6 days respectively. How many children were required with 1 man and 1 woman to complete the same work in (...
- ‘A’ alone can complete a work in 40 days while ‘A’ and ‘B’ together can complete the same work in 30 days. How much percentage of the work, ‘B’ alone can c...
- A work is done by A, B, C and D together. The percentage of work done by A, B C and D are in arithmetic progression (AP). The first, second, third and four...
- 'Aman' and 'Bittu' alone can do some work in 30 days and 45 days, respectively. They work together for eleven days after which both 'Aman' and 'Bittu' are ...
- Abhay, Beer, and Tittu have individual work completion times of 12 days, 24 days, and 36 days, respectively. They Started working together on a task. After...
- Peter and Rachel can complete a project together in 20 days. Peter takes four times as long as Rachel to complete the same project alone. Find the time tak...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)