Question
Brahma, Vishnu and Mahesh are three workers, employed by a Contractor. They completed the whole work in 20 days. Initially all of them worked together, but the last 60% of the work was completed by only Vishnu and Mahesh together. Brahma worked with Vishnu and Mahesh only for initial four days then he left the work due to his poor health. Also, Vishnu takes 25% less time to finish the work alone than that of Mahesh working alone. If they were paid Rs. 24500 for the entire work, then what is the share of least efficient person?
More Time and work Questions
- "'Mahesh' is 40% less efficient than 'Neeraj.' 'Neeraj' takes 30 days fewer than 'Mahesh' to finish the same work. Find the time taken by 'Neeraj' to finis...
- Bharti, Chiku, and Diksha complete 30%, 40%, and 20% of a task in 6 days, 12 days, and 8 days, respectively. How many days will it take for them to collect...
- P, Q, and R can do a project individually in 10, 25, and 20 days. P and Q begin the project, but after 2 days, P is replaced by R. How many more days will ...
- If Ankit takes four times the time that Ravi takes or five times the time that Sandeep takes to finish a task, and all three working together can complete ...
- Ratio of the work done by P, Q and R in one day is 7:3:8 respectively. They all together can complete the work in 42 days. Q and R worked on it for 21 days...
- Komal and Seema individually can complete a task in ‘3a’ hours and ‘7a’ hours respectively. If they together can complete (2/3)rd of the work in 7 hours, t...
- Suppose ‘n’ employees can process all the files in 50 days. If 10 more employees had participated, the work would be completed in 30 days. Find the value o...
- A2 type ‘P’ pipes can fill a tank in 450 hours, while B2 type ‘Q’ pipes can fill the same tank in 648 hours. (10A × 6B) type ‘P’ pipes can fill the same ta...
- A and B together can complete a piece of work in 30 days while A alone can complete 50% of the work in 25 days. Find the time taken by B to complete 80% of...
- 'P' and 'Q' can finish a piece of work in 45 days and 90 days, respectively. 'P' starts working alone, and 'Q' joins after 'r' days, ensuring that the enti...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)