Question
A job is done by 15 men in 30 days and 30 women in 20
days. How many days will it take for 8 men and 12 women to finish the work?Solution
15 men × 30 days = 450 Women’s 1-day work = 450/(30× 20) = ¾ work (8 Men + 12 Women)’s 1-day work = 8 +12 × ¾ = 17 Days taken by 8 M and 12 women to finish the work = 450/17 days Alternate Method: 15 Men can do this job in 30 days and 30 women can do this job in 20 days It means 45 men or 60 woemn can do this job in = 10 days So 8 Men and 12 women can do this job in = 10/{8/45 + 12/60} = 10/ {8/45+ 1/5} = 10 /{17/45} = 450 /17
Under the Liberalised Remittance Scheme, all resident individuals, including minors, are allowed to freely remit up to USD ______ per financial year.
Which of the following is not the work of RBI?
Which feature distinguishes a current account from a savings account?
Consider the following statement/s about Companies Act 2013:
1. It received presidential assent on 29 August 2013.
2. It superseded the Co...
In which of the following year the State Bank of India has launched a unified integrated app called YONO (You Need Only One)?
Which of the following is NOT an example of manufacturing activity?
Which financial institution in India operates the Pradhan Mantri Mudra Yojana (PMMY), aimed at providing loans to micro enterprises?
Securities and Exchange Board of India (SEBI) works under the administrative domain of which ministry?
According to the data provided by the government, foreign direct investment (FDI) into India declined 34 per cent to _______during April-June 2023-24, d...
The inaugural officeholder of the chairperson of State Bank of India was?