A can do a piece of work in 12 days, while B alone can do it in 18 days. They work together for 6 days and the rest of the work is completed by C in 4 days. If they get Rs. 720 for the whole work, how should they divide the money?
Work done by A and B in 6 days = (1/12 + 1/18) × 6 = 5/6 Work remaining = 1 - 5/6 = 1/6 ∴ C alone can do the work in 6 × 4= 24 days Ratio of their share work = 6/12 : 6/18 : 4/24 = 3:2:1 Share of A’s wages = 3/6 × 720 = Rs. 360 Share of B’s wages = 2/6 × 720 = Rs. 240 Share of C’s wages = 1/6 × 720 = Rs. 120
What is the primary goal of the Malaviya Mission - Teacher Training Programme launched by the University Grants Commission and the Ministry of Education?
SEBI has imposed a penalty of _________on Shapoorji Pallonji and Company for flouting disclosure norms & not taking prior approval from the stock exchan...
Which country collaborated with India to establish a Center of Water Technology at IIT-Madras?
Recently, two Indian scientists from the National Institute of Oceanography (NIO), and their team have discovered an active submarine volcano (Crater Se...
World Breastfeeding week 2022 was celebrated from ____?
According to the survey by credit rating agency S&P Global, Purchasing Managers' Index (PMI) declined marginally to 61.2 in May from its 13-year high of...
Tata Group-led Air India placing landmark orders of 500 aircrafts from _____ as Air India prepares to transform itself under the Tata Group.
What does BRO stand for in the context of Indian infrastructure?
Recently the “Yuva Sangam” registration portal was launched at which city?
How has India's position in the global mobile phone production market changed by the end of the decade 2014-2024?