Question

    A can do a piece of work in 12 days, while B alone can do it in 18 days. They work together for 6 days and the rest of the work is completed by C in 4 days. If they get Rs. 720 for the whole work, how should they divide the money?

    A Rs. 300, Rs. 200, Rs. 220 Correct Answer Incorrect Answer
    B Rs. 360, Rs. 140, Rs. 220 Correct Answer Incorrect Answer
    C Rs. 300, Rs. 240, Rs. 180 Correct Answer Incorrect Answer
    D Rs. 360, Rs. 240, Rs. 120 Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    Work done by A and B in 6 days = (1/12 + 1/18) × 6 = 5/6 Work remaining = 1 - 5/6 = 1/6 ∴ C alone can do the work in 6 × 4= 24 days Ratio of their share work = 6/12 : 6/18 : 4/24 = 3:2:1 Share of A’s wages = 3/6 × 720 = Rs. 360 Share of B’s wages = 2/6 × 720 = Rs. 240 Share of C’s wages = 1/6 × 720 = Rs. 120

    Practice Next
    ×
    ×