Question
In an office, an employee plans to do a work in 20 days
with 6 laptops. But after 10 days, he found that only 40% of the work is done with the laptops working for 6 hours a day. If he want to complete the work in the planned time with the laptops, how many hours per day the laptops have to work?Solution
Laptops do 40% of the work in 10 days, or 10 × 6 = 60 hours. So the rest of the (i.e., 60% of the work) can be done in, => (60 × 60)/40 = 90 hours This 90 hours of work has to be done in the remaining (20 – 10) = 10 days. Laptops have to work (90/10) = 9 hours a day to complete the work in the planned time.
Which one of the following is not. the same as the other three ?
The widely used 7-bit ASCII code is employed:
To save an existing file with new name at a new location we should us _______ command.
Which type of computer security attack involves exploiting software vulnerabilities that have not been patched or updated?
URL stands for
Holding the mouse button down while moving an object or text is known as _________.
Non impact printer
Which one is the Open-source operating system?
What does a light pen contain?Â
Which of the following options is used to check spelling and grammar in a Microsoft Word document?