Question
In an office, an employee plans to do a work in 20 days with 6 laptops. But after 10 days, he found that only 40% of the work is done with the laptops working for 6 hours a day. If he want to complete the work in the planned time with the laptops, how many hours per day the laptops have to work?
More Time and work Questions
- P is 60% more efficient than Q. P takes 30 more days to finish a work as compared to the number of days taken by P and Q together to finish the same work. ...
- 40 laborers were hired to finish a construction job in 50 days. After 35 days of work, only 62.5% of the job was done. How many additional laborers are nee...
- A can finish a piece of work in 15 days and B can finish it in 20 days. They work together for 4 days and then B leaves. In how many more days can A alone ...
- 18 skilled workers can complete a task in 12 days while 24 semi-skilled workers need 15 days to complete the same task. 12 skilled workers started the task...
- P and Q together can do a piece of work in 15 days, Q and R together can do it in 18 days. P starts the work and works on it for 5 days, then Q takes it up...
- Ram can finish a task alone in 45 days, whereas Ram and Rahul working together can complete the same task in 12 days. If Rahul works on the task alone for ...
- A’ and ‘B’ together can complete a work in 15 days while ‘A’ takes 20 days to complete the same work alone. If ‘C’ is 50% more efficient than ‘B’, then fin...
- 12 men can complete a work in 10 days, while 10 women can complete the same work in 18 days. In how many days will 4 men and 6 women complete the work toge...
- A can copy 70 pages in 25 hours, A and B together can copy 135 pages in 25 hours. Then in how many hours B can copy 10 pages.
- A and B can complete a piece of work in 12 days, B and C in 15 days and A and C in 20 days. In how many days can B alone complete the work?
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)