Virat can do a piece of work in 26 days and Sachin can do the same work in 39 days. If Virat works for 5 days and got Rs. 3000, and the remaining work will completed by Sachin, then how much rupee Sachin earned?
Assume total work = LCM (26, 39) = 78 If the entire work is 78 units, Virat can complete 3 unit per day, and Sachin can complete 2 unit per days In 5 days, Virat completes 15 units and got Rs.3000 i.e. Rs.200 per unit. Remaining work = (78 – 15)unit = 63 unit ∴ Sachin earning = Rs.63 × 200 = Rs. 12600
What is the time period under which Pre-Packaged Resolution process should be completed from the date of initiation?
What new financial instrument did Airtel Payments Bank launch in collaboration with NPCI and powered by RuPay?
Banks are required to use External Benchmark lending rate for which of the following types of the loans:
What do ethics most closely relate to?
Which method is a common accounting method of depreciation wherein an asset’s value depreciates at twice the rate it would under straight-line depreci...
Who has issued the guidelines on the import of gold by Tariff Rate Quota (TRQ) holders under the India-UAE Comprehensive Economic Partnership Agreement ...
The Sustainable Development Goals (SDGs) India Index measures the Indian States on the basis of the progress made on various Sustainable Development Goa...
What does CGRA expand to?
Which ministry launched the ‘DigiClaim’ platform under the national crop insurance portal for speedy disbursal of claims to insured farmers?
Which of the following gives the Fisher equation of money?