Question
Aβ and βBβ together can complete a work in 15 days
while βAβ takes 20 days to complete the same work alone. If βCβ is 50% more efficient than βBβ, then find the time taken by βCβ alone to complete the whole work.Solution
Let the total work = 60 units Efficiency of (A + B) = 60/15 = 4 units/day Efficiency of βAβ = 60/20 = 3 units/day Therefore, efficiency of βBβ = 4 β 3 = 1 unit/day Efficiency of βCβ = 1.5 Γ 1 = 1.5 units/day Required time taken = 60/1.5 = 40 days
Which family does Gerbera belong to ?
TSS of jelly should be more then
Which medicinal plant is known as winter cherry ?
In guava, water is withheld in which month of hasta bahar?
Which fruit is commonly known as βFruit of New WorldβΒ
What is the term for the method used to separate leaf pigments in green plants?
The popular variety of mango which is suitable for high density planting is
Bitter pit in Apple is due to the deficiency of _________
Which is an example of a false fruit, formed from parts other than the ovary wall?
Which fruit is also referred to as "Bathroom fruit" ?