Let the total work = 80 units Efficiency of (X + Y) = 80/16 = 5 units/day Efficiency of (Y + Z) = 80/10 = 8 units/day Efficiency of ‘Y’ = 80/20 = 4 units/day Efficiency of (X + Y + Z) = (1 + 4 + 4) = 9 units/day Required time taken = (0.45 × 80)/9 = 4 days