A and B together, B and C together and A and C together can complete a piece of work in 14 days, 15 days and 18 days respectively. Find the ratio of the efficiencies of A, B and C, respectively.
Let, the total work be 630 units (LCM of 14, 15 and 18) Amount of work done by A and B together in one day = 630/14 = 45 units Amount of work done by B and C together in one day = 630/15 = 42 units Amount of work done by A and C together in one day = 630/18 = 35 units Amount of work done by A, B and C together in one day = (45 + 42 + 35)/2 = 61 units Amount of work done by A alone in one day = 61 – 42 = 19 units Amount of work done by B alone in one day = 61 – 35 = 26 units Amount of work done by C alone in one day = 61 – 45 = 16 units So the desired ratio = 19:26:16
Which of the following is not a type of muscle tissue?
In April 2023, which Tiger Reserve secured the top position in the Excellence category during the 5th Management Effectiveness Assessments?
Which of the following is not a mosquito borne disease ?
What is the time limit for the payment of gratuity to an eligible employee under the Act?
Bhed Mata Mela is associated with which animal?
Which individuals have received the "Order of White Eagle" from Poland in April 2023?
The selling price of the book is 40% more than the selling price of the bag and the selling price of the bottle is 20% less than the selling price of th...
Which of the below mentioned steps are likely to cause the appreciation of rupee against dollar?
1. Increase limit of FPI in Indian Bond market...
Which of the following pairs is wrongly matched ?
Vasco da Gama discovered the new and all-sea route from Europe to India and landed on 17th May 1498 at: