Question

    A isthrice as efficient as B and can finish a piece of work in 32 days less than B. B can finish this work in how many days?

    A 40 days Correct Answer Incorrect Answer
    B 48 days Correct Answer Incorrect Answer
    C 52 days Correct Answer Incorrect Answer
    D 45 days Correct Answer Incorrect Answer

    Solution

    Ratio of efficiencyof A and B = 3: 1
    A will take 1/3 of time as compared to B.
    Say, B takes 3x days and A takes x days.
    ∴ 3x – x = 32 ⇒ x = 16
    ∴ B takes 16 × 3 = 48 days to do the work.

    Practice Next
    ×
    ×