90 men can complete a work in 32 days. Eight days after they started working, 72 more men joined them. How many days will they now complete the remaining work ?
From: M1D1/W2 = M2D2/W1 90 × 32 = (90 × 8) + (90 + 72) × D2 D2 = 3 days (approx.)
According to the UNFPA's 'India Ageing Report 2023,' what percentage of India's total population is projected to be aged 60 years and above by the year ...
India will be supplying 40 Mega Watt Power supply to which country recently?
What is the primary focus of the Dubai Gaming Visa introduced by the Crown Prince of Dubai?
Which organization will generate the Unique Identification Number (UID) for doctors in India?
The World Bank has approved an ______ loan towards the adoption of global best practices for animal health management to prevent, detect, and respond to...
Which of the following system enabling the citizens of the country to utilize any ATM of a connected bank?
Who among the following has/have been honored with “special, posthumous homage” at the Martin Ennals Award in Geneva?
The ‘Tripartite struggle’ was between Gurjara Pratiharas in North India, Palas in Eastern India and ________ in South India.
Which bank announced the introduction of its all-new Privy League programme, an exclusive premium banking programme with unique lifestyle benefits and...
What is the distinctive feature of the newly discovered lizard species, Agasthyagama edge or northern kangaroo lizard?