Question
A can do a work in 10 days and B in 15 days. If they
work on it together for 4 days then in how many days the remaining work will be completed by B?Solution
Total work = Number of days × 1 day’s work (efficiency) Total work = LCM (10, 15) = 30 unit 1 day’s work of A = 30/10 = 3 unit 1 day’s work of B = 30/15 = 2 unit 1 day’s work of (A + B) = 3 + 2 = 5 unit Now, 4 day’s work of (A + B) together = 4 × 5 = 20 unit Remaining work = 30 – 20 = 10 Remaining work completed by B = 10/2 = 5 days
Statements:
D ≤ E > I; Q ≤ I ≤ W; F = W ≥ Y
Conclusions:
I. E > Q
II. F ≥ I
Which of the following day is off?
Which of the following items is contained in Box 5?
Who conducts workshop on Saturday?
Who among the following lives exactly between the floors on which E and A live?Â
Which of the following box is at the top?
Which of the following combination is true?
How many persons attend the seminar between the one who uses BMW and U?
Who among the following persons opted both Physics and Accountancy?
Which among the following combinations is/are true?
I. Nakul and the one belongs to Kanpur were born in the month having 31 days.
II. One ...