Total work = Number of days×1 day’s work (efficiency) Total work = LCM (12, 16) = 48 unit 1 day’s work of A = 48/12 = 4 unit 1 day’s work of B = 48/16 = 3 unit 1 day’s work of (A + B) = 4 + 3 = 7 unit Now, 3 day’s work of (A + B) together = 3× 7 = 21 unit Remaining work = 48 – 21 = 27 Remaining work completed by B = 27/3 = 9 days
Who is the new Chairman of ICC (2025)?
At the Cannes Film Festival 2023, which pavilion felicitated American actor Michael Douglas and provided him with a warm welcome?
Which National Park in India is home to a rare dwarf goat breed called "kanchu mekha" locally?
Which of the following is NOT true about India’s economic growth projections?
Who was appointed chief adviser of Bangladesh's interim government by President Mohammed Shahabuddin in August 2024?
Which city hosted the 32nd International Conference of Agricultural Economists (ICAE 2024) in August 2024?
According to the recent report released by Forbes, who is the highest earning player in the world?
Match the following international treaties with their focus areas:
The Environmental Performance Index (EPI) is jointly released by which two universities?
Which ministry is responsible for the Jal Jeevan Mission?