Question
A does 2/5 of a work in 9 days. Then B joined him and
they together completed the remaining work in 6 days. B alone can finish the whole work inSolution
If A can complete 2/5 of work in 9 days, then he can complete whole work in (9×5)/2 = (9×5)/2 = 22.5 days. Let B take x number of days to complete the work. According to question, (2/45 + 1/x) × 6 = 3/5 x = 18 days. So, the answer would be option d) 18 days
स्वदेशी आंदोलन शुरू किया गया था ?
How much capital expenditure did India’s private sector achieve in FY 2024-25, as projected by a recent RBI study?
Increased competition by bringing more private sector banks and foreign banks, reduced the share of Public Sector Banks in total loans.
Grey revolution was related to ____________.
Who was the President of the Independence for India league' formed in 1928?
Which organization was penalized ₹50,000 by the RBI in October 2024 for non-compliance with KYC regulations?
Name the joint military exercise which was conducted between the special forces of Russia and Pakistan recently?
On which day is Krishna Janmashtami celebrated during the dark fortnight of Bhadrapada?
India's smallest Union Territory Lakshadweep has how many islands?
The first phase of bank nationalization began in the year of