Question
A does 2/5 of a work in 9 days. Then B joined him and
they together completed the remaining work in 6 days. B alone can finish the whole work inSolution
If A can complete 2/5 of work in 9 days, then he can complete whole work in (9×5)/2 = (9×5)/2 = 22.5 days. Let B take x number of days to complete the work. According to question, (2/45 + 1/x) × 6 = 3/5 x = 18 days. So, the answer would be option d) 18 days
In which type of farming do farmers grow crops mainly to feed their families?
A boat will submerge when it displaces water equal to its own:
India’s first greenfield grain based ethanol production plant inaugurated in ………………….
Heat energy transmitted through collisions between neighboring atoms or molecules is called ________.
The yearly sequence and spatial arrangement of crops or of crops and fallow on a given area is known as
…………………………State Government has launched the trees outside forest in India programme in association with USAID.
...The scientific study of diseases in plants, identification of the pathogen and their management is known asÂ
Who has been designated as the "Youth Voter Awareness Ambassador" for Jammu & Kashmir by the Election Commission of India?
The theme for the Word food Day, which was observed on 16th October 2022 was:
The world’s largest coral reef isÂ