Question

    X men can complete the piece of work in 50 days and (X + 51) men can complete the same work in 30 days less than that of days taken by X men. Find the value of X. 

    A 34 Correct Answer Incorrect Answer
    B 42 Correct Answer Incorrect Answer
    C 55 Correct Answer Incorrect Answer
    D 44 Correct Answer Incorrect Answer
    E 63 Correct Answer Incorrect Answer

    Solution

    According to question, => X × 50 = (X + 51) × 20 => 50X = 20X + 1020 => 30X = 1020 => X = 34

    Practice Next

    Relevant for Exams:

    ×
    ×