Question
Karan, Arjun and Krunal alone can complete a work in 30,
45 and 36 days respectively. All of them started working together but after 3 days from start Karan left the job and after 5 more days Arjun also left the job. So for how many days did Krunal work?Solution
Let the total work = 180 units (LCM of 30, 45 and 36) Amount of work done by Karan alone in one day = 180/30 = 6 units Amount of work done by Arjun alone in one day = 180/45 = 4 units Amount of work done by Krunal alone in one day = 180/36 = 5 units Amount of work done by Karan, Arjun and Krunal together in 3 days = 3 × (6 + 4 + 5) = 45 units Amount of work done by Arjun and Krunal together in 5 days = 5 × (4 + 5) = 45 units Remaining work = 180 – 45 – 45 = 90 units So, the time taken by Krunal alone to complete 90 units work = 90/5 = 18 days So, Krunal worked for 18 + 5 + 3 = 26 days
Which vow is not among the Five Great Vows of Jainism?
The Emblem of the Chola Dynasty was
Which country has India’s Ministry of MSME signed an MoU with to promote cooperation on SMEs?
In which state the 9th edition of the 'Amur Falcon Festival' celebrated on 21st November, 2024?
With reference to the Global Initiative on Sharing All Influenza Data (GISAID), consider the following statements:
1. It aims to promote the rapi...
Which Brahmana text details the journey of King Videgha Madhava with his priest, Rishi Gautama Rahugana?
Which statements about millets are true?
(I) Kutki and Sanwa are the varieties of Millets.
(II) The earliest evidence of Millets consumpti...
Narsasimha Varman I was also known as Mamallan means
Which of the following dynasty is also known as the Mamluk Dynasty?
Which of the following factors made the kingdom of Avanti, the most serious competitor of Magadha? Â
1. Availability of Iron ore mines.
...