Let the total work = 96 units (LCM of 24, 48 and 32) Amount of work done by A alone in one day = 96/24 = 4 units Amount of work done by B alone in one day = 96/48 = 2 units Amount of work done by C alone in one day = 96/32 = 3 units Amount of work done by A, B and C together in 2 days = 2 × (4 + 2 + 3) = 18 units Amount of work done by B and C together in 3 days = 3 × (2 + 3) = 15 units Remaining work = 96 – 18 – 15 = 63 units So, the time taken by C alone to complete 63 units work = 63/3 = 21 days So, C worked for 21 + 2 + 3 = 26 days
Select the set in which the numbers are related in the same way as are the numbers of the following sets.
(NOTE : Operations should be performed ...
Statements:
Some Necklaces are Rings.
All Rings are Bracelet.
Only a few Rings are Ornaments.
Conclusion:
I. All Brac...
Which word will best complete the relationship given below?
Bricklayer : Trowel :: Tailor : ?
If 5459 = 450, 2485 = 160 and 8763 = 504, then 3474 = __.
If 35 @ 18 = 66 and 49 @ 22 = 136, then 23 @ 44 = '?'.
Study the given pattern carefully and select the number that can replace the question mark (?) in it.
HJG : MOL :: (?) : WUX
There are 5 cartons E, F, G, H & I placed on table. If E is placed below I, G is placed above H, F is placed below E and H is placed above I, then which...
RT : QU : : VX : ?
If 51 @ 24 = 9' and 56 @ 22 = 8', then 72 @ 32 = ?'. What will come in place of question mark?