Question
Work efficiency of Chacha and Bhatija are in the ratio
of 3 : 1. They working together to do a piece of work and completed the work in 24 days. Now in how many days the total work be finish if Chacha working alone?Solution
Work efficiency of Chacha : Bhatija = 3 : 1 Total work done = 3 + 1 = 4 units then Total work done = 4 × 24 = 96 units Required time = 96/ 3 = 32 days
Which ISRO center developed the Global Navigation Satellite System-Reflectometry (GNSS-R) instrument?
A documentary named “A Son of Himalaya” is being made on the life struggle of a great personality of the state?
In which state is the famous Amer Fort located? Â
Which organization administers and regulates the National Pension System (NPS)?
What initiative has Assam’s government launched to provide financial support to girl students and prevent child marriages?
Identify the Indian state that does not share its borders with Nepal.
Who assumed the role of the 12th Governor of Jharkhand recently?
In which Indian state is the Amaravati Stupa, a significant archaeological site, located?Â
Rajesh Agarwal has been appointed as the new ambassador to
First-ever female UK Ambassador to United Nations (UN) _______________Â