Question
P can do a piece of work in 25 days, Q can complete
double the work in 40 days and R can do the work in 30 days. If all of them together earn Rs. 7400, then find the money received by Q.Solution
Time taken by P = 25 days Q can complete double the work in 40 days Time taken by Q in a work = 20 days Time taken by R = 30 days Let the total work be 300 units. P’s one day work = 12 units Q’s one day work = 15 units R’s one day work = 10 units Amount received by Q = 7400 × (15/37) = Rs. 3000
- 80% of a number is the same as 64% of another number. If their combined value is 360, find the difference of the numbers.
- A town's population increased by 5% in the first year, increased by 15% in the second year, and decreased by 9% in the third year. If the population in 202...
- In a school election between two contestant’s 'A' and 'B', 'A' secured 62% of the total votes and won by 7,440 votes. Find how many votes 'B' got.?
Monthly savings of ‘A’ is Rs. 700 more than his monthly expenditure and his total monthly income is Rs. 6500. If his monthly income is increased by ...
J's salary is 35% less than V's salary, then how much percent more or less is J's salary compared to G's salary, given that G's s...
The value of A’s car is depreciating by 30% every year whereas the value of his house is appreciating by 9% each year as compared to the previous year...
The marked price of an article is 30% higher than the cost price. If a trader sells the articles allowing 10% discount to customer, then the gain percen...
A batsman scored 124 runs, which included 6 boundaries and 10 sixes. What percentage of his total score did he make by running between the wickets?
A gave 40% of amount to B. B gave 30% of amount received from A to C. If amount received by C from B is Rs.144, then find the amount received by B from A.
Out of his income of Rs. 50,000, Ravi spent 25% on food, 15% of the remaining income on clothing, and saved the rest. If he would have spent Rs. 200 mor...