Question

    P can do a piece of work in 15 days, Q can complete double the work in 60 days and R can do the work in 40 days. If all of them together earn Rs. 3000, then find the money received by Q.

    A Rs.1000 Correct Answer Incorrect Answer
    B Rs.800 Correct Answer Incorrect Answer
    C Rs.1200 Correct Answer Incorrect Answer
    D Rs.900 Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    Time taken by P = 15 days Time taken by Q = 30 days Time taken by R = 40 days Let the total work be 120 units. P’s one day work = 8 units Q’s one day work = 4 units R’s one day work = 3 units Amount received by Q = 3000 × (4/15) = Rs. 800

    Practice Next
    ×
    ×