P can do a piece of work in 15 days, Q can complete double the work in 40 days and R can do the work in 20 days. If all of them together earn Rs. 3000, then find the money received by Q.
Time taken by P = 15 days Time taken by Q = 20 days Time taken by R = 20 days Let the total work be 60 units. P’s one day work = 4 units Q’s one day work = 3 units R’s one day work = 3 units Amount received by Q = 3000 × (3/10) = Rs. 900
What was the profession of Prime Minister of Japan, Shinzo Abe before it?
In which of the following cities in the United States of America, Yugantar Ashram, the headquarter of Gadar Party, a liberation movement of India, was e...
Which of the following is correctly matched?
The Central Intelligence Agency of the USA has appointed whom as the CIA's first-ever Chief Technology Officer (CTO)?
What is the tenure of the Panchayati Raj institution?
Who was the first Odissi dancer from Odisha to receive Padma Vibhushan?
As per Budget 2023 -24, how much comes from cooperation tax for every 1 Re receipt of the government?
What is the first step of the process of staffing in an organisation?
The national digital data repository of India is known as?
Cricketer Zaheer Khan was awarded the ______ in 2020.