Question
A and B can complete a work together in 30 days. If A alone can complete one-third of the work in ‘x’ days and remaining work is completed by B alone in 2x days, then find the value of
A and B can complete a work together in 30 days. If A alone can complete one-third of the work in ‘x’ days and remaining work is completed by B alone in 2x days, then find the value of
x.
More Time and work Questions
- Kabir can build a fence in 16 days. Working together, Kabir and Arjun can finish it in 8 days. How long will Arjun take to build the fence alone?
- ‘P’ can complete 40% of a task in 24 days, while ‘Q’ can complete 25% of the task in 20 days. How long will it take approximately for ‘P’ and ‘Q’ together ...
- A and B alone can complete a work in 15 and 30 days, respectively. 50% of the work is completed by C in 2x days, and the remaining work is completed by A a...
- Ratio of the work done by P, Q and R in one day is 7:4:9 respectively. They all together can complete the work in 44 days. Q and R worked on it for 30 days...
- P can complete a piece of work in 15 days. Q in 20 days and R in 30 days. P and R worked together for three days and then P was replaced by Q. In how many ...
- A and B together can finish a job in ‘x’ days, while A alone takes ‘x + 32’ days to complete it. B alone can finish the job in 90 days. If C is 20% more ef...
- A team of ‘a’ mechanics can finish a repair job in 6 days. But every day exactly 12 mechanics remain absent. Hence, the job is finished in 1/2 more time th...
- A and B together can complete a work in 6 days, B and C together in 8 days, and C and A together in 12 days. In how many days can each of them complete the...
- The efficiency ratio of D, E, and F is 1:2:5. Together, they complete a project in 16 days. If D and E contribute for 14 days and leave, how long will F ta...
- A work can be completed by ‘A’ and ‘B’, alone in 10 days and 15 days, respectively. Find the number of days taken by ‘C’ to complete the same work alone if...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)