Question
A and B alone can complete a work in 15 and 30 days, respectively. 50% of the work is completed by C in 2x days, and the remaining work is completed by A and B working together in ‘x’ days. Find the time taken by B and C to complete the whole work while working together.
More Time and work Questions
- A can complete a piece of work in 80 days, B takes 20% more time than A to complete the same work while C takes 25% more time than B to complete the whole ...
- Raj, Sanjay and Vaibhav can separately finish a work in 20, 30 and 40 days, respectively. In how many days Raj can finish the work if he is assisted.by San...
- A takes 30% longer to complete a task than B. If the total payment for the work is Rs. 11,500 and they complete the task together, how much should A be pai...
- ‘A’ can finish a project in 40 days, whereas ‘B’ finishes 50% of the project in 12 days less than ‘A’. How many days will it take both ‘A’ and ‘B’ to compl...
- A and B can jointly finish a task in 42 days, while B and C together take 35 days to finish the same task. If B can finish the task alone in 105 days, how ...
- Before 'A' joined the team, 'S' and 'V' were alternating days to complete a project. In the final four days, 'A', 'S', and 'V' all worked together to finis...
- A and B can complete a task together in 22 days, while B alone takes 44 days to finish it. A began working alone and left after ‘x’ days, after which B com...
- A and B can complete a work together in 36 days. If A alone can complete one-third of the work in lsquo;xrsquo; days and remaining work is completed by B a...
- Sonal completed 30% of work alone and left the remaining work for Vinod who completed it in 28 days. If the total work got completed in 40 days, then find ...
- If ‘P’ can complete a task in 24 days and ‘P’ with ‘Q’ together can finish it in 15 days, then how many days will ‘Q’ take to complete the work alone?
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)