A, B and C alone can complete a work in 30, 60 and 45 days respectively. All of them started working together but after 3 days from start A left the job and after 7 more days B also left the job. So for how many days did C work?
Let the total work = 180 units (LCM of 30, 60 and 45) Amount of work done by A alone in one day = 180/30 = 6 units Amount of work done by B alone in one day = 180/60 = 3 units Amount of work done by C alone in one day = 180/45 = 4 units Amount of work done by A, B and C together in 3 days = 3 × (6 + 3 + 4) = 39 units Amount of work done by B and C together in 7 days = 7 × (3 + 4) = 49 units Remaining work = 180 – 39 – 49 = 92 units So, the time taken by C alone to complete 92 units work = 92/4 = 23 days So, C worked for 23 + 3 + 7 = 33 days
6 boys and 8 girls can do a piece of work in 12 days. 7 boys and 11 girls can do the same piece of work in 10 days. In how many days can 2 boys and 6 g...
When working alone, Ansh takes 12 more days than time taken by Ansh and Balu together to finish certain work. If Ansh is 50% more efficient than Balu, t...
A can do a piece of work in 28 days, while B can do the same piece of work in 42 days. They begin working together and 6 days before completion of work,...
P’s 4 days work is equal to Q’s 5 days work. If P and Q together can complete the work in 20 days then how much time Q will take to complete 40% of ...
"Amit" and "Bhanu" have respective completion times of 20 and 30 days for a task. They began working together on the project, but after a few days, "Ami...
A alone can complete 60% of a work in 24 days while B takes 20 days more than A to complete it. If B and C together can complete the work in 35 days, th...
Find the value of "w" if Armaan can complete a Sales target in (w + 20) days, Malik can complete it in (w + 44) days, and when they work together, they ...
Saurabh can complete a piece of work in 20 days. He worked for 5 days and left. Anirudh completed the remaining work in 12 days. If both of them had do...
A2 type ‘P’ pipes can fill a tank in 450 hours, while B2 type ‘Q’ pipes can fill the same tank in 6...
A is thrice as efficient as B and can finish a piece of work in 20 days less than B. B can finish this work in how many days?