138 unit of work can be completed by P alone in 23 days.
P started working alone and joined by Q after 11 days such that they completed the remaining work in 8 days. Find the number of days taken by Q to complete the whole work alone.Solution
Let the efficiency of Q = x units/day Efficiency of P = (138/23) = 6 units/day According to question: 6 × 11 + (6 + x) × 8 = 138 Or, 66 + 48 + 8x = 138 Or, 8x = 138 – 114 Or, 8x = 24 Or, x = 3 Number of days taken by Q to complete the work alone = (138/3) = 46 days
Recently the Union Minister Dr. Jitendra Singh inaugurate the “Jhula Bailey Suspension Bridge” in which of the following State/UT?
According to WHO’s Mental Health Atlas 2024, what percentage of Indian adults suffer from mental disorders?Â
According to the Air Quality Life Index (AQLI) 2025 report, how many years of life expectancy do residents of Delhi-NCR lose due to air pollution?Â
Incentives paid by the government to banks for promoting RuPay debit cards and low-value BHIM-UPI transactions will not attract _______.
What was the purpose of laying the keel of Yard 1283 NGOPV in Goa on June 9, 2025?Â
Which Indian state topped NITI Aayog’s Fiscal Health Index 2025?
What was India’s rank in the 2025 Global Digital Competitiveness Index released by IMD?Â
- What are the revised investment and turnover limits for medium enterprises under the new MSME classification?
Which site was designated as India’s 13th UNESCO Biosphere Reserve in 2025?Â
What is the theme of the IICA North-East Conclave 2025 held in Shillong?Â