138 unit of work can be completed by P alone in 23 days.
P started working alone and joined by Q after 11 days such that they completed the remaining work in 8 days. Find the number of days taken by Q to complete the whole work alone.Solution
Let the efficiency of Q = x units/day Efficiency of P = (138/23) = 6 units/day According to question: 6 × 11 + (6 + x) × 8 = 138 Or, 66 + 48 + 8x = 138 Or, 8x = 138 – 114 Or, 8x = 24 Or, x = 3 Number of days taken by Q to complete the work alone = (138/3) = 46 days
If DBC = 18 and GFE = 36, then IJEF =
Select the correct option that indicates the arrangement of the given words in the order in which they appear in an English dictionary.
1. Presti...
Statement :
No stool is a desk.
Some desk are tables.
All tables are chairs.
Some chairs are benches.
Conclusion :�...
Select the set of numbers that is similar to the following set of numbers.
{19, 27, 35}
Which of the following boxes is placed immediately above and immediately below N?
What is the difference between the floor number of G and F?
Arrange the given words in the sequence in which they occur in the dictionary.
i. Realistic
ii. Reason
iii. Reached
iv. Reassure
V. Rear
Which Answer Figure will complete the pattern in the figure?
A group of letters are numbered from 1 to 8. Four options given below depict combinations of these numbers. Select that combination of numbers so that l...
Which letter-cluster will replace the question mark (?) in the following series?
CAE, EYG, HVJ, ?, QMS