126 unit of work can be completed by P alone in 21 days.
P started working alone and joined by Q after 10 days such that they completed the remaining work in 4 days. Find the number of days taken by Q to complete the whole work alone.Solution
Let the efficiency of Q = x units/day Efficiency of P = (126/21) = 6 units/day According to question: 6 × 10 + (6 + x) × 4 = 126 Or, 60 + 24 + 4x = 126 Or, 4x = 126 – 84 Or, 4x = 42 Or, x = 10.5 Number of days taken by Q to complete the work alone = (126/10.5) = 12 days
The ratio of P’s to Q’s salary is 5 : 7. If Q’s salary is increased by 35%, his total salary becomes Rs. 52,920. What is the salary of P?
- There are 65 students in a class. Rs.78 is distributed among them such that each boy gets 2(6/13)% of the total students and each girl gets 12/13 % of the ...
Find the third proportional to 14 and 70?
What number has to be added to each term of 2:3 to make the ratio 4:5?
- The ratio of the number of candies with Charu and Disha is 7:5. Disha's father gave her 4 more candies after while Charu stole 33(1/3)% candies possessed b...
Ratio of monthly income to monthly expenditure of A is 19:7, respectively and monthly savings of A is Rs. 2400. Find the monthly income of A.
The ratio of the salaries of Amit, Raj, and Dev is 5:6:7 respectively. Sumit’s salary is 10 rupees less than Amit’s. If the difference between Dev ...
What is the fourth proportion of 18, 20 and 23?
The ratio of the monthly salary of Supriya to that of Mohini is 3 : 5. Supriya and Mohini both save 30% and 42% respectively of their monthly salaries r...
Total population of city P and Q is 4030 and 6300 respectively. If the ratio of number of males to females in city is P and Q is 9:4 and 4:3 respectivel...