Question
126 unit of work can be completed by P alone in 21 days. P started working alone and joined by Q after 10 days such that they completed the remaining work in 4 days. Find the number of days taken by Q to complete the whole work alone.
More Time and work Questions
- A is thrice as efficient as B and can finish a piece of work in 20 days less than B. B can finish this work in how many days?
- A and B can complete a task together in 14 days, while B alone takes 28 days to finish it. A began working alone and left after ‘x’ days, after which B com...
- Akhil and Nikhil together can complete a work in 9 days while Nikhil alone takes 12 days to complete 50% of the work. If the efficiency of Sachin is 20% mo...
- 'B' alone can complete a work in 24 days while 'A' and 'B' together can complete the same work in 8 days. 'A' alone started the work and left after 4 days ...
- X men can complete the piece of work in 32 days and (X + 30) men can complete the same work in 15 days less than that of days taken by X men. Find the valu...
- A alone can complete a work in 18 days and B alone can complete it in 27 days. They work together for 6 days and then B leaves. In how many more days will ...
- The efficiency ratio of workers A and B is 15:17. If both A and B collaboratively finish a task in 30 days, how long would it take for A to complete the ta...
- Brahma, Vishnu and Mahesh are three workers, employed by a Contractor. They completed the whole work in 20 days. Initially all of them worked together, but...
- ‘A’ can do a piece of work in 15 days. ‘B’ can do 60% of the same work in 20 days. If they work together for the entire time and get paid Rs.1450, then fin...
- 50 workers working 6 hours a day take 18 days to complete a task. How many workers working for 5 hours a day are needed to complete four times the given ta...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)