Question
P and Q can complete a work in 28 days and 42 days,
respectively. P, Q and R together can complete the work in 14 days. If R get a total wage of Rs. 5460 to complete the work alone, then find the per day wage of R.Solution
Let the total work be LCM of (28, 42 and 14) = 84 units Number of units of work done by P alone in one day = 84/28 = 3 units Number of units of work done by Q alone in one day = 84/42 = 2 units Number of units of work done by P, Q and R together in one day = 84/14 = 6 units Number of units of work done by R alone in one day = 6 – 3 – 2 = 1 unit So, time taken by R alone to complete the work = 84/1 = 84 days So, per day wage of R = 5460/84 = Rs. 65
In photosynthesis, what does ATP stand for?Â
Which new genus of jumping spiders, discovered in South India, was named in October 2024?
Which one among the following statements is correct?Â
Whitening of hair is caused by the deficiency of _________.
Which is the smallest bone in the human body?
Which bodily fluids are known to contain pheromones?
Which of the following represents the pair of sex chromosomes in men?
Which among the following is not a connective tissue?
Which technique is employed for DNA detection?
Which of the following is water borne disease?