Question
Chacha and Bhatija can complete a work in 48 days. In
how many days Chacha alone does the 2/3rd of the total work if they start working together after 40 days Chacha left the work, work is completed in 52 days.Solution
=> 1/Chacha + 1/Bhatija = 1/48 If, Chacha leaves the work after working 40 days with Bhatija, then the whole work is completed in 52 days. Therefore, Bhatija alone works for 12 days. => 40 (1/Chacha + 1/Bhatija) + 12/Bhatija = 1 => (40 × 1/48) + 12/Bhatija = 1 => 5/6 + 12/Bhatija = 1 => 12/Bhatija = 1 – 5/6 => 12/Bhatija = 1/6 => Bhatija = 72 Then, 1/Chacha = 1/48 – 1/72 => Chacha = 144 Chacha alone can complete the whole work in 144 days. And, Chacha can do 2/3rd of the work in = (144 × 2/3) days = 96 days.
If A+B means ‘A is the daughter of B’, A-B means ‘A is the wife of B’, A×B means ‘A is the father of B’, A÷B means ‘A is the son of B’...
Select the option figure in which the given figure is embedded (rotation is NOT allowed).
Select the word-pair in which the two words are related in the same way as are the two words in the following word-pair.
Butterflies : Lepidopterist
Two statements are given, followed by three conclusions numbered I, II and III. Assuming the statements to be true, even if they seem to be at variance...
If 54 [9] 3 and 108 [30] 5, then what is the value of Z in 19 [Z] 18?
On which of the following days the RRB PO seminar was held?
Odd one out
What will come in place of ‘a’?
Four number pairs have been given, out of which three are alike in some manner and one is different. Select the one that is different.
If + means −, − means ×, × means ÷, and ÷ means +, what will be the value of the following expression?
3 ÷ 6 + 3 – 4 × 4 = ?
...