Akhil and Nikhil together can complete a work in 5 days while Nikhil alone takes 10 days to complete 40% of the work. If the efficiency of Sachin is 25% more than that of Akhil, then find the time taken by Sachin alone to complete the whole work.
Time taken by Nikhil to complete the whole work alone = 10/0.40 = 25 days Let the total work = 25 units Efficiency of (Akhil + Nikhil) = 25/5 = 5 units/day Efficiency of Nikhil = 25/25 = 1 units/day Efficiency of Akhil = 5 - 1 = 4 units/day Therefore efficiency of Sachin = 1.25 x 4 = 5 units/day Time taken by Sachin to complete the whole work alone = 25/5 = 5 days
With respect to Aspirational Block Programme (ABP), consider the following statement:
I. It aimed at improving performance of blocks lagging on v...
What initiative has the Ministry of Coal taken for the disposal and repurposing of fly ash?
Who has recently taken oath as the First Woman Minister of Nagaland?
Which scheme launched by Telangana Chief Minister A. Revanth Reddy provides ₹1 lakh financial assistance to Civil Services aspirants who qualify for t...
When was the windfall tax on crude oil producers first introduced in India?
What is the budget allocation for the Mahatma Gandhi National Rural Employment Guarantee Scheme (MGNREGS) in the Union Budget for 2024-25, which aims to...
The Ministry of Electronics and Information Technology (MeitY) has signed 3 MoUs to boost research & development (R&D) and skilling in artificial intell...
BimaKavach has received a direct insurance broking licence from the Insurance Regulatory and Development Authority of India (IRDAI), enabling the firm t...
Who has been selected for the Kerala Sangeetha Nataka Akademi fellowship in the field of Chenda/Edakka?
What is the primary objective of the Memorandum of Understanding (MoU) signed between India and the UAE regarding education?