Question
Akhil and Nikhil together can complete a work in 10 days
while Nikhil alone takes 20 days to complete 40% of the work. If the efficiency of Sachin is 25% more than that of Akhil, then find the time taken by Sachin alone to complete the whole work.Solution
Time taken by Nikhil to complete the whole work alone = 20/0.40 = 50 days Let the total work = 50 units Efficiency of (Akhil + Nikhil) = 50/10 = 5 units/day Efficiency of Nikhil = 50/50 = 1 units/day Efficiency of Akhil = 5 - 1 = 4 units/day Therefore efficiency of Sachin = 1.25 x 4 = 5 units/day Time taken by Sachin to complete the whole work alone = 50/5 = 10 days
The measure of the force that can cause an object to rotate about an axis is called:
How many new metro projects were inaugurated by Prime Minister Modi in January 2025?
The Mumbai Metropolitan Region Development Authority (MMRDA) recently signed an agreement with which company to provide financial support of over Rs 850...
Which of the following company had buys 89% stake in Purple Panda Fashions recently?
National Payments Corporation of India (NPCI) has launched some new payment features. What new payment features has it launched to promote digital inclu...
Why do pickles last longer?
What is the projected job creation from the PLI scheme as mentioned in the export performance data?
The eMobility Simulation Lab will have the latest tools along with financial support from Altair & will carry out other e-mobility labs for batteries,...
Which Indian Navy ship, commissioned in Russia, marks the last foreign-built warship in its fleet?
What is the purpose of the Prime Minister's Mentorship Scheme for Young Writers (PM-YUVA Scheme)?