Question

    A work can be completed by ‘A’ and ‘B’, alone in 10 days and 12 days, respectively. Find the number of days taken by ‘C’ to complete the same work alone if ‘A’, ‘B’ and ‘C’ together can complete the whole work in 4 days.

    A 10 days Correct Answer Incorrect Answer
    B 14 days Correct Answer Incorrect Answer
    C 15 days Correct Answer Incorrect Answer
    D 11 days Correct Answer Incorrect Answer
    E None of these Correct Answer Incorrect Answer

    Solution

    Let total work = 60 units (LCM of 10 and 12) Efficiency of ‘A’ = (60/10) = 6 units/day Efficiency of ‘B’ = (60/12) = 5 units/day Combined efficiency of ‘A’, ‘B’ and ‘C’ = (60/4) = 15 units/day Efficiency of ‘C’ = 15 – (6 + 5) = 4 units/day Required time taken = (60/4) = 15 days

    Practice Next