Question
A work can be completed by βAβ and βBβ, alone in
12 days and 18 days, respectively. Find the number of days taken by βCβ to complete the same work alone if βAβ, βBβ and βCβ together can complete the whole work in 4 days.Solution
Let total work = 36 units (LCM of 12 and 18) Efficiency of βAβ = (36/12) = 3 units/day Efficiency of βBβ = (36/18) = 2 units/day Combined efficiency of βAβ, βBβ and βCβ = (36/4) = 9 units/day Efficiency of βCβ = 9 β (3 + 2) = 4 units/day Required time taken = (36/4) = 9 days
Which district has become the first district in India to 100% link the Aadhaar number with a Voter ID card?
What is accumulation hazard?
Which Section of the IRDAI Act,1999 specifies the Duties, Powers and functions of the Authority?
Personal and business property coverage combining several types of property insurance in one policy is called?
What is the primary method to calculate the pure premium for a group of insured?
What is the purpose of a "loss adjuster"?
A generic term applying to all types of insurance indemnifying or reimbursing for losses caused by bodily injury or illness including related medical ex...
Which of the following is a combination of insurance as well as investment ?
Which type of insurance can covers two or more items or location ?
What is the primary function of a reinsurer?