Question
‘A’ and ‘B’ can do a piece of work in 22 days
and 25 days, respectively. If they started the work together and worked on it for 6 days, then find the time taken by ‘B’ alone to complete the remaining work.Solution
Let total amount of work be 550 units Efficiency of ‘A’ = 550/22 = 25 units/day Efficiency of ‘B’ = 550/25 = 22 units/day Amount of work done by ‘A’ and ‘B’ together in 6 days = (25 + 22) × 6 = 282 units Time taken by B to complete remaining work = (550 – 282)/22 = 134/11 days
The process of separating lint from seed in cotton is called ___
Debt equity ratio is:
Hydrophytes are known as
Who started to work on cereal rust in India?
Phenyl mercuric acetate (PMA) is a ______ of antitranspirant.
Experimental design in which two experimental errors are calculated is
When both the alleles of gene are fully expressed in a heterozygote, what is this phenomenon called?
Crazy Chick disease in poultry is caused due to the deficiency of which of the following?
Relay intercropping is
The branch of Horticulture that deals with the cultivation of vegetables is called