πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!


    Question

    A buffalo alone can plough field β€˜A’ in 15 days. A

    Bull alone can plough the field β€˜A’ in 25 days. Find the number of days taken by 2 bulls and 3 buffalo to together plough field β€˜B’ that is 26% larger than field β€˜A’?
    A 4.5 days Correct Answer Incorrect Answer
    B 3.5 days Correct Answer Incorrect Answer
    C 5.5 days Correct Answer Incorrect Answer
    D 7.5 days Correct Answer Incorrect Answer

    Solution

    Let the total work done to plough field β€˜A’ = 75 units (LCM of 15 and 25) Then, efficiency of a buffalo = (75/15) = 5 units/day Efficiency of a bull = (75/25) = 3 units/day Total work required to plough field β€˜B’ = 75 Γ— 1.26 = 94.5 units Combined efficiency of 2 bulls and 3 buffalo = 3 Γ— 2 + 3 Γ— 5Β = 21 units So, number of days required to plough field β€˜B’ = 94.5/21 = 4.5 days

    Practice Next
    ask-question