Question
‘A’ alone can complete a work in 40 hours. ‘A’ started the work alone and left after working on it for 20 hours. If ‘B’ completed the rest of the work in 20 hours then find the time taken by ‘A’ and ‘B’ together to complete the whole work.
More Time and work Questions
- ‘C’ and ‘D’ can complete a piece of work together in 24 days. If ‘C’ alone can complete it in 40 days, how long would ‘D’ take to do the same work alone?
- A group of 16 women can complete a certain job in 48 days, working 7 hours each day. How many women would be required to complete the same job in 32 days, ...
- ‘A’ and ‘B’ can do a piece of work in 12 days and 15 days, respectively. If they started the work together and worked on it for 2 days, then find the time ...
- A can do a piece of work in 15 days, B is 25% more efficient than A, and C is 40% more efficient than B. A and C work together for 3 days and then C leaves...
- 12 man can make a wall in 6 days. How many men required to complete the same work in 3 days ?
- 5 men and 6 women can do some work in 3 days. If each man is 50% more efficient than a woman, then find the time taken by 9 men to finish the same work tog...
- A can do a piece of work in 24 days. B can do the same work in 16 days and C can do the same work in 5/4th time required by both A and B together. A and B ...
- Sonal completed 30% of work alone and left the remaining work for Vinod who completed it in 28 days. If the total work got completed in 40 days, then find ...
- A can finish a job in 20 days while B can finish same job in 30 days. A and B both worked for 5 days and C joins them. In next 3.5 days, all three have man...
- Ratio of the work done by P, Q and R in one day is 7:4:9 respectively. They all together can complete the work in 44 days. Q and R worked on it for 30 days...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)