55 men can complete a piece of work in 12 days. 15 men started the same work and worked for 10 days, and then joined by ‘x’ more men such that the remaining work is completed in 10 days. Find the value of ‘x’.
According to the question, 55 × 12 = 15 × 10 + (15 + x) × 10 Or, 660 = 150 + 150 + 10x Or, 660 - 300 = 10x Or, x = 36
Consider the following statements in regards to the Economic Survey of India 2022-23:
1. 315.7 million tonnes of food grains produced in I...
Which of the following dynasties is not related to the southern part of India?
Which one of the following pairs of crops in India is the most water – gugging crops of India that depend heavily on ground water?
SVEEP is the flagship program of which of the following organisation?
Which Panwar ruler fostered positive relations between Garhwal and Kumaon during their reign?
What exactly is UHT processing used for processing?
PAN is currently required for cash deposits of Rs _____ or more per day.
Where is the Sahara desert located in the following countries / continents?
The height of the Dancing Girl figurine of Indus Valley Civilization is about _________.
Where is the National Bureau of Agriculturally important Micro-organiom situated in Uttar Pradesh?