Question

    30 men can complete a piece of work in 11 days. 15 men started the same work and worked for 8 days, and then joined by ‘x’ more men such that the remaining work is completed in 6 days. Find the value of ‘x’.

    A 20 Correct Answer Incorrect Answer
    B 24 Correct Answer Incorrect Answer
    C 20 Correct Answer Incorrect Answer
    D 28 Correct Answer Incorrect Answer

    Solution

    According to the question, 30 × 11 = 15 × 8 + (15 + x) × 6 Or, 15 + x = (330 – 120) ÷ 6 Or, 15 + x = 35 Or, x = 20

    Practice Next

    Relevant for Exams:

    ×
    ×