‘A’ and ‘B’ can do a piece of work in 30 days and 40 days, respectively. They started working together but ‘A’ left after 9 days. Find the time taken by ‘B’ to complete the remaining work.
Let total amount of work be 120 units (LCM of 30 and 40). Efficiency of ‘A’ = 120/30 = 4 units/day Efficiency of ‘B’ = 120/40 = 3 units/day Amount of work done by ‘A’ and ‘B’ together in 9 days = (4 + 3) × 9 = 63 units Time taken by B to complete remaining work = {(120 – 63)/3} = 19 days
Which country has announced the release of a new ₹100 note depicting the Indian territory?
Which of the following group of gases contributes to the "Green House Effect"?
Researchers at which institute recently developed an innovative method to efficiently generate hydrogen gas from a mixture of methanol and paraformaldeh...
“Gramin and Krishi Vikas Samiti” was established at which place?
The salaries of the Supreme Court judges are determined by _______.
What was the primary aim of the significant meeting between India and the UAE about the India-Middle East-Europe Economic Corridor (IMEEC)?
In the annual Gender Gap Report for 2023, what rank did India achieve in terms of gender parity?
The Union Cabinet approved ______ worth of investments in three semiconductor plants, including a Tata group proposal to build the country’s first maj...
Which of the he following statements is/are correct about Intelligent Grievance Monitoring System (IGMS) 2.0:
1. It is a public grievance porta...
Union Minister for Education and Skill Development & Entrepreneurship Dharmendra Pradhan, along with the Chief Minister of which state, inaugurated the ...