‘A’ and ‘B’ can do a piece of work in 30 days
and 40 days, respectively. They started working together but ‘A’ left after 9 days. Find the time taken by ‘B’ to complete the remaining work.Solution
Let total amount of work be 120 units (LCM of 30 and 40). Efficiency of ‘A’ = 120/30 = 4 units/day Efficiency of ‘B’ = 120/40 = 3 units/day Amount of work done by ‘A’ and ‘B’ together in 9 days = (4 + 3) × 9 = 63 units Time taken by B to complete remaining work = {(120 – 63)/3} = 19 days
The World Bank has revised India’s GDP growth outlook for FY26 to what percentage?Â
How much investment has been approved for the National Critical Mineral Mission (NCMM)?
Which state topped the medal tally at the Khelo India Water Sports Festival 2025 in Srinagar?Â
What benefit does the West Bengal government’s Shramashree scheme provide to migrant workers returning to the state?Â
What is the expected emission reduction by 2035, according to the UNEP Emissions Gap Report 2024, to meet the 1.5°C target?
What is the total stake NLC India Renewables Limited holds in its joint venture with MAHAPREIT?
Consider the following statements regarding BRICS:
       I.           The term BRICS was coined by the British Economist Jim...
How many contaminated sites have been identified under the Environment Protection (Management of Contaminated Sites) Rules, 2025?Â
Which IIM ranked in the top 100 in the QS Global MBA Rankings 2025?
What is the projected size of India’s mining equipment market by 2033?Â