Question
A can complete a work in 30 days. B takes 6 days less
than A to complete the same work. In how many days can both of them together complete 60% of the work together?Solution
Time taken by B to complete the work = 30 – 6 = 24 days Let the total work = 120 units Efficiency of A = 120/30 = 4 units/day Efficiency of B = 120/24 = 5 units/day Required time taken = 0.60 x 120/(4+5) = 8 days
Chiasmata Formation takes place in which stage?
What causes puffy fruit in tomatoes ?
The oldest crop improvement method is:
Breeder seed is the progeny ofÂ
Which citrus pest causes damage by consuming leaves from the margin and is most destructive during the nursery stage of the crop?
The oil content in Groundnut is:
Inheritance of ABO blood group system is an example of____
The only known nickel containing enzyme
Which one of the following is C: N ratio for most of the oil cakes?
Which of the following Agricultural commodity of Uttarakhand recently got GI tag?