A’ and ‘B’ together can complete a work in 10 days
while ‘A’ takes 18 days to complete the same work alone. If ‘C’ is 25% more efficient than ‘B’, then find the time taken by ‘C’ alone to complete the whole work.Solution
Let the total work = 90 units Efficiency of (A + B) = 90/10 = 9 units/day Efficiency of ‘A’ = 90/18 = 5 unit/day Therefore, efficiency of ‘B’ = 9 – 5 = 4 units/day Efficiency of ‘C’ = 1.25 × 4 = 5 units/day Required time taken = 90/5 = 18 days
Who has been appointed as the Director of the Liquid Propulsion Systems Centre of ISRO?
Consider the statements about World Heritage Committee:
1. India takes the chair of World Heritage Committee for the first time.
2. It is ...
According to NITI Aayog, which district has been declared first among the 112 aspirational districts of the country in the basic infrastructure theme?
How many Urban Cooperative Banks (UCBs) had their licenses revoked by the RBI in 2024 alone?
Which Indian ministry oversees the ASEAN-India Fellowship for Higher Education in Agriculture and Allied Sciences?
‘Vishu’ is which state’s New Year festival?
What is the primary goal of the upcoming program 'Kisano Ki Baat' by the Indian government?
With reference to “Blockchain Technology”, consider the following statements: (2020)
1.It is a public ledger that everyone can inspect, but w...
What is the name given to the operation launched to bring back Indians stranded in Israel
In which year was the University Grants Commission (UGC) established?