Question
A’ and ‘B’ together can complete a work in 10 days while ‘A’ takes 18 days to complete the same work alone. If ‘C’ is 25% more efficient than ‘B’, then find the time taken by ‘C’ alone to complete the whole work.
More Time and work Questions
- 108 unit of work can be completed by P alone in 18 days. P started working alone and joined by Q after 9 days such that they completed the remaining work i...
- ‘A’ can complete a work in 20 days and is 20% more efficient than ‘B’. ‘A’ and ‘B’ start the work together, but ‘A’ leaves after 10 days. The remaining wor...
- Komal and Seema individually can complete a task in ‘3a’ hours and ‘6a’ hours respectively. If they together can complete half of the work in 6 hours, then...
- 9 children can complete a piece of work in 360 days. 18 men can complete the same piece of work in 72 days and 12 women can complete the piece of work in 1...
- 42 men can complete 3/5 part of a work in 8 days working 9 hours a day. How many women can complete rest of the work if they work for 6 hours a day for 42 ...
- 18 men working for 6 hours a day can complete a work in 22 days. If 27 women are employed to work, then find how many hours a day they have to work to comp...
- If Ankit takes four times the time that Ravi takes or five times the time that Sandeep takes to finish a task, and all three working together can complete ...
- Rahul does half the work done by Karan in 2/3 of the time. If they together can complete the work in 14 days, how much time will Karan take to complete the...
- A and B together can finish a job in 12 days. B alone takes 30 days. How long will A and C together take to finish the same job if C does one-fourth of A’s...
- ‘P’ alone can complete a work in 25 days while ‘P’ and ‘Q’ together can complete the whole work in 15 days. Find the time taken by ‘Q’ alone to complete th...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)