Question

    If 12 men working 12 hours a day can make 12 quilts in 12 days, then in how many days 24 men working 24 hours per day will make 24 quilts?

    A 9 Correct Answer Incorrect Answer
    B 6 Correct Answer Incorrect Answer
    C 5 Correct Answer Incorrect Answer
    D 7 Correct Answer Incorrect Answer

    Solution

    Let the number of days be x. According to question, => (12 ×  12 ×  12)/12 = (x ×  24 ×  24)/24 => x = 6