Question

    If 14 men working 14 hours a day can make 14 quilts in 14 days, then in how many days 28 men working 28 hours per day will make 28 quilts?

    A 9 Correct Answer Incorrect Answer
    B 6 Correct Answer Incorrect Answer
    C 5 Correct Answer Incorrect Answer
    D 7 Correct Answer Incorrect Answer

    Solution

    Let the number of days be x. According to question, => (14 ×  14 ×  14)/14 = (x ×  28 ×  28)/28 => x = 7