Question
If 18 men working 18 hours a day can make 18 quilts in 18 days, then in how many days 27 men working 12 hours per day will make 27 quilts?
More Time and work Questions
- If 3 men can finish a task in 4 days, and 4 women can complete the same task in 9 days, how many days will it take for a team of 2 men and 6 women working ...
- 'A' and 'D' together can finish a project in 40 days. If 'D' alone can complete 25% of the project in 15 days, then find out how long it takes for 'A' alon...
- Question 3
- 'X' and 'Y' can complete a certain job together in 36 days. They worked together for 20 days, after which 'X' left, and 'Y' completed the remaining work al...
- If 12 men can build a wall in 15 days, how many men are required to build the same wall in 10 days?
- ‘X’ and ‘Y’ together can complete a work in 16 days, while ‘Y’ and ‘Z’ together can complete the work in 10 days. If ‘Y’ takes 20 days to complete the work...
- Anoop and Bhanu together can finish a certain piece of work in 90 days, while Bhanu and Charu together can complete the work in 70 days. Bhanu, Charu, and ...
- 'P' and 'Q' together can complete a task in 20 days. 'P' alone would take 12 days fewer than 'Q' to finish it. How many days would 'Q' take to do the work ...
- A group of 36 boys works 13 hours per day and completes 37.5% of a task in 20 days. After these 20 days, 'X' boys leave the job. The remaining boys continu...
- ‘P’ is 25% more efficient than ‘Q’. ‘Q’ worked alone for 6 days and then ‘P’ finished the rest of the work in 4 days. How many days would ‘Q’ alone take to...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)