Ashish and Anil can do a piece of work in 12 days and 15
days respectively. Ashish completed 30% of the work. Find the time taken by Anil to complete the remaining work.Solution
Let the total work be (LCM of 12 and 15) = 60 units Efficiency of Anil = 60/15 = 4 units/day Remaining work = 60 x 0.7 = 42 units Time taken by Anil to complete the remaining work = 42/4 = 10.5 days
In which state is Kolleru Lake located?
Book Title 'Gandhi and Champaran Satyagraha: Select readings, who has edited the book?
The Panama Canal connects which two bodies of water?
Recently the Union Ministry of Panchayati Raj organized two day National Training Workshop on People’s Plan from _____ to ______ October...
Consider the following statements about the RudraM-II missile tested by DRDO:
1. It is designed for surface-to-air engagements.
2. The m...
The Reserve Bank of India (RBI) has directed which card networks to cease their Business Payment Solution Provider (BPSP) operations?
Which article of the Indian Constitution stipulates that the Chairman or Deputy Chairman shall not preside during their removal proceedings?
Who become the first female President of Hungary?
The Asian Development Bank (ADB) approved a USD 200 million loan for the expansion of metro rail corridors in which Indian city in July 2024?
What was the theme for “World Milk Day” this year?