Ashish and Anil can do a piece of work in 10 days and 18
days respectively. Ashish completed 75% of the work. Find the time taken by Anil to complete the remaining work.Solution
Let the total work be (LCM of 10 and 18) = 90 units Efficiency of Anil = 90/18 = 5 units/day Remaining work = 90 x 0.25 = 22.5 units Time taken by Anil to complete the remaining work = 22.5/5 = 4.5 days
In a code language, CROPS is written as '15’ and BAJRA is written as '2'. How will MILLETS be written in that language?
Find the odd one out
The second number in the given number pairs is obtained by performing certain mathematical operation(s) on the first number. The same operation(s) is/a...
Four letter-clusters have been given, out of which three are alike in some manner and one is different. Select the letter-cluster that is different.Â
Four letter-clusters have been given, out of which three are alike in some manner and one is different. Select the letter-cluster that is different.
Find the ODD one out from the given options.
Select the odd group of numbers. (NOTE: Operations should be performed on the whole numbers, without breaking down the numbers into its constituent dig...
Find the odd word from the given alternatives.
Four words have been given, out of which three are alike in some manner and one is different. Select the odd word.
Which of the following letter cluster is the odd letter cluster?