Question

    Ashish and Anil can do a piece of work in 15 days and 25

    days respectively. Ashish completed 40% of the work. Find the time taken by Anil to complete the remaining work.
    A 15 days Correct Answer Incorrect Answer
    B 18 days Correct Answer Incorrect Answer
    C 10 days Correct Answer Incorrect Answer
    D 7 days Correct Answer Incorrect Answer

    Solution

    Let the total work be (LCM of 15 and 25) = 75 units Efficiency of Anil = 75/25 = 3 units/day Remaining work = 75 x 0.6 = 45 units Time taken by Anil to complete the remaining work = 45/3 = 15 days